Major Little Hulton roadworks begin on Monday for 17 weeks

Published

on

The works will affect the Manchester Road East, Manchester Road West, Cleggs Lane, and Armitage Avenue junction until mid-October, as resurfacing work is undertaken and a new crossing is installed.

Local contractor Rosgal Ltd will be the company to undertake the works, on behalf of the commissioner, Salford Council.

(Image: Dan Dougherty)

The works will take place in four phases in an attempt to ‘minimise disruption,’ according to Salford Council.

Working hours will be between 9.30am and 3.30pm, with temporary traffic light signals and road closures in place.

Advertisement

The ‘North East’ quadrant – Cleggs Lane – will take place between June 22 and July 10.

The ‘South East quadrant – Manchester Road East – will take place between July 13 and 31 July.

The ‘South West’ quadrant – Armitage Avenue – will take place between August 3 and August 21.

The ‘North West’ quadrant – Manchester Road West – will take place between August 24 and September 14.

Advertisement

(Image: Dan Dougherty)

Several buses pass through this junction as they travel between Bolton, Little Hulton, Walkden, and Manchester, including the 36, 38, and 20.

If the works are completed on schedule, they should be finished by October 12.

Lewis Croden, City Councillor for Little Hulton Said:” While we appreciate these works will cause temporary disruption, they are essential to create a safer, better-functioning junction for pedestrians and all road users.

“We’ve phased the project to keep impacts to a minimum over the 17-week period.”