Tech

Queensland and NT reject Australia’s data centre energy rules

Published

on

Australian Prime Minister Anthony Albanese’s proposed national environmental and energy controls for the country’s A$150 billion data centre pipeline hit their first obstacle on Tuesday, when two jurisdictions declined to back them. Federal, state and territory energy ministers met virtually to discuss the plan, and Queensland and the Northern Territory opposed most of the measures, including the idea of a national rulebook at all.

The structural problem is that the policy requires unanimity. Every state and territory must support the federal framework for it to proceed, which gives any single jurisdiction an effective veto.

What the rules would require

New data centres would have to add at least as much electricity generation to the grid as they consume, a requirement Albanese set out in a policy speech earlier in July. He described bringing these issues into a single national framework as a global first.

Operators would also be expected to build renewable generation, minimise water use, maximise energy efficiency, and fund any additional water infrastructure they need. Albanese offered few details on how any of it would work in practice.

Advertisement

Why Queensland objects

Queensland Premier David Crisafulli had signalled his position before the announcement, saying the state does not support imposing renewable power requirements because it wants to stay attractive to investors. That is precisely the behaviour the national framework was designed to prevent.

“The policy the PM has announced doesn’t work unless there’s buy-in from all the states and territories,” said Rob Nicholls, a senior researcher at the University of Sydney’s Centre for AI, Trust and Governance. “Part of the reason you have a policy is to avoid a race to the bottom from the states.”

The industry is broadly onside, with conditions

Belinda Dennett, chief executive of industry group Data Centres Australia, whose members include Google, AirTrunk, and Microsoft, said the group supports the principle that new electricity demand should be backed by new supply. Many operators and customers already underwrite renewable energy, she noted.

The industry wants clarity on three points. Whether the compliance obligation sits with the operator or the tenant, when it takes effect, and whether the offset is measured against actual electricity consumption or nameplate capacity.

Advertisement

That third question is not a technicality. Nameplate capacity is typically far higher than real-world draw, so the answer could change the size of the obligation by a wide margin.

The public is well ahead of the politics

A YouGov survey commissioned by Australia’s Climate Council found 82% of respondents agreed that new data centres should pay for the extra renewable energy and storage infrastructure needed to meet their power demand. The measure is not short of popular support.

The economics also cut both ways. Data centre investment could reach A$150 billion by 2030 with six gigawatts of planned capacity, according to Commonwealth Bank associate economist Lucinda Jerogin, and the construction boom is helping prop up a slowing economy.

Why Australia is a target market

Australia was second only to the United States in dollars invested in data centres in 2024, according to Knight Frank. Bloomberg Intelligence analysts led by Matt Ingram flagged the country in June as one of Asia’s top build locations, citing renewable potential, political stability, and low-latency submarine cables to the rest of the region.

Advertisement

Demand is coming from hyperscalers including Microsoft and Meta, alongside opposition from community and environmental groups. Both pressures are intensifying at once.

Everyone is grappling with the same problem

Australia is not alone in trying to attach conditions to compute. Brussels has told Big Tech to align AI data centres with climate goals or stay away, insisting operators support clean power and recycle waste heat.

Where regulators hesitate, grids are imposing their own limits. Denmark paused all new grid connection agreements after a 60-gigawatt queue overwhelmed the cleanest power system in Europe, a physical constraint no policy framework can negotiate away.

Ambitious clean-power targets have proved hard to hit. China wants renewables to supply roughly four-fifths of its AI data centre power by 2030, up from about 11% in 2023, a target its own grid is struggling to accommodate.

Advertisement

The default alternative is worse. The AI buildout has triggered the largest construction boom in gas-fired power plants on record, which is the outcome Australia’s additionality rule is designed to avoid.

What happens next

The federal government will work with states, territories, and market bodies on detailed policy design, with the possibility of more stringent local requirements layered on top. Energy ministers meet again in September.

National Cabinet is expected to consider the approach in August, with legislation anticipated in early 2027. Whether it arrives intact depends on whether Queensland and the Northern Territory can be persuaded that a national floor beats competing on who asks the least.

Advertisement

Source link

You must be logged in to post a comment Login

Leave a Reply

Cancel reply

Trending

Exit mobile version