Pipeline for $165 Billion Oracle Data Center Delayed to Next Year

Published

on

The Green Chile pipeline that would fuel Oracle’s Project Jupiter data centre in New Mexico has been pushed from 15 August to 1 February 2027, according to a filing by Energy Transfer’s Transwestern unit. The state land commissioner has twice refused the route, citing water use and emissions.

The pipeline that would fuel Oracle’s largest planned data centre has slipped by nearly six months. Energy Transfer’s Transwestern unit told federal regulators on Friday that the Green Chile Project now has an in-service date of 1 February 2027, against a previous target of 15 August.

What it feeds is not a normal building. Project Jupiter in Doña Ana County is planned at 2.5 gigawatts, powered by Bloom Energy fuel cells, with Oracle as the tenant hosting AI infrastructure for OpenAI.

The numbers around it are large in every direction. Developers Stack and BorderPlex Digital Assets have talked of investing up to $165bn across 1,400 acres and four buildings, at a company already borrowing heavily to build data centres. The pipeline would carry up to 400 million cubic feet of gas a day, roughly 0.4% of everything produced in the lower 48 states.

Advertisement

Standing in the way is one elected official. New Mexico land commissioner Stephanie Garcia Richard has refused the route twice, first in March and again on 15 July, because it crosses state trust land.

Her reasoning was not procedural. The project would benefit investors and developers but bring “no significant benefits for state lands,” she wrote, calling the burden on New Mexico’s water and natural resources “extreme.

She was blunter still on emissions, describing approval as “literally doubling down on dangerous emissions” at a moment when the state should be slowing climate change rather than accelerating it.

Oracle has made its own urgency clear. It told the Federal Energy Regulatory Commission in May that “time is of the essence” and that delay would jeopardise “the broader objectives of Project Jupiter.

Advertisement

The fuel cells were already the compromise. Bloom’s solid oxide units replaced planned gas turbines and diesel generators, and Oracle has since expanded that order to 2.8GW, but they still burn gas, which is the pattern across an industry running on fossil fuel while promising otherwise.

Investors read it as a setback. Oracle shares fell about 4% on Friday, while Energy Transfer rose 1.4%.

The lesson is about land rather than capital. Money and chips can be bought at speed, but a 17-mile right of way cannot, and 500 US towns have already blocked data centres of their own.

Advertisement

Source link

Continue Reading
Click to comment

You must be logged in to post a comment Login

Leave a Reply

Tech

Zoox has shown its safety workings, three weeks after recalling every robotaxi it owns

Published

on

Zoox has published the reasoning behind its claim to be safer than human drivers. Everything reduces to one number, the predicted rate of collision, injury and fatality events, expressed as miles per event. Risk from driving software, from the vehicle itself and from fleet operations is added together into that single estimate.

It functions as a gate. Before any safety-relevant software release, hardware change or revision to operating procedure, Zoox updates the case and checks the combined figure still clears its target.

The target is anchored in human data. Zoox builds its benchmark from NHTSA’s crash sampling and fatality reporting systems and two Federal Highway Administration datasets, then parses them by road speed and weights them to match the mix of roads its robotaxis actually use.

What it does not publish is the answer. Zoox sets its target by comparison to that benchmark and says it aims to be significantly safer than a human driver, but never defines how much safer counts as significant. Nor does it give the figure its fleet currently reaches.

Advertisement

The engineering underneath is specific enough to argue with. Zoox names the hazard analyses it runs, follows ISO 26262 with integrity ratings on the platform, and uses simulation that deliberately searches for the conditions where a collision is most likely, weighted afterwards by real fleet exposure.

Some of it is genuinely unusual. A separate collision checker runs its own perception and can veto a trajectory the main system has planned, and Zoox concedes that a likelihood-based metric cannot capture rare avoidance scenarios, so it keeps a test set where the robotaxi must at least match a competent human.

Remote staff are inside the model rather than outside it. TeleGuidance tacticians never drive, offering route guidance while the vehicle keeps responsibility, and the risk of them making a mistake or their tools failing is priced into the same estimate.

The framework also reserves the right to restrict, pause or ground the fleet. Three weeks before publishing it, Zoox recalled all 105 of its robotaxis after one failed to detect heavy smoke and drove into an active fire scene in Las Vegas.

Advertisement

That was the fourth software recall in roughly 13 months, and it followed the regulator demanding fixes for vehicles interfering with first responders. NHTSA had logged 123 collisions involving Zoox vehicles in autonomous mode as of March.

The analytical approach exists because the mileage does not. Zoox has around three million autonomous miles, Waymo passed a hundred million more than a year ago, and Zoox now has a paid service to protect while it closes that gap.

Source link

Advertisement
Continue Reading

Tech

How to watch Australia vs Japan: Free streams & TV channels

Published

on

Watch Australia vs Japan live streams as the Wallabies look to follow up their hard-fought 35-32 victory over the Brave Blossoms with a more comprehensive victory on home soil in Townsville, Queensland.

The first game in the post-Joe Schmidt era proved to be a tough one for Australia as they were forced to hang on for a narrow win in Osaka. Surviving a first-half red card for Miles Amatosero and a second-half onslaught from Japan, new head coach Les Kiss would have been nervy on the touchline. He’ll hope for a more convincing display on home soil and has opted for Carter Gordon at fly-half instead of Declan Meredith.

Source link

Advertisement
Continue Reading

Tech

OpenAI CFO tells shareholders enterprise revenue has overtaken ChatGPT

Published

on

OpenAI’s enterprise business now generates more revenue than its consumer business, finance chief Sarah Friar told shareholders on Friday, months earlier than the company had forecast. Its annualised run rate has reached $40bn, roughly double a year ago.

OpenAI now makes more money from businesses than from ChatGPT subscribers. Finance chief Sarah Friar told shareholders on Friday that the two lines have crossed, according to a person at the meeting. “We entered the year at 60-40, but enterprise has accelerated much faster than expected,” she said.

That is early. Friar had said earlier this year that the two sides of the business would reach parity by the end of 2026.

The underlying numbers are moving quickly. OpenAI’s annualised run rate has reached $40bn, roughly double a year ago, and July revenue rose 20% month on month, with business customers up 32%.

Advertisement

More interesting is what enterprise buyers have started doing. “Enterprise customers have moved from tokenmaxxing to focusing on cost per unit of intelligence,” Friar said, meaning companies have stopped letting staff run up open-ended AI bills without showing what came of them.

OpenAI is answering on price rather than resisting. Friar pointed to recent cuts across its model range and to the newest model being 54% more efficient on agentic coding tasks.

Advertising has quietly become a business too. It is approaching a $1bn run rate, six months after OpenAI began testing ads in ChatGPT in February.

The meeting itself was scheduled before the week went wrong. It came a day after revenue chief Denise Dresser left after eight months and three days after longtime executive Brad Lightcap announced his departure.

Advertisement

President Greg Brockman thanked Dresser for building the enterprise foundation, the attendee said. He also praised her replacement, Dali Rajic, who was introduced to OpenAI by Thrive founder Josh Kushner, according to a person familiar with the recruiting.

Asked about Chinese open-source models, Brockman was dismissive. There is a misunderstanding that open source is cheaper, he said.

On the listing, nothing. Executives told shareholders they could not discuss timing because of the confidential filing with the SEC.

Advertisement

Source link

Continue Reading

Tech

Talks to sell PayPal to Stripe and Advent are heating up

Published

on

PayPal CEO Enrique Lores’ turnaround plan for the fintech company could include a sale — of itself.

The prospect first popped in July when Stripe and private equity giant Advent offered to buy PayPal for $60.50 a share in a deal that would have valued it at $53 billion, the Wall Street Journal reported at the time.

PayPal balked. But apparently, negotiations never stopped and a deal could come together in the coming weeks, according to new reporting by the WSJ, which cited unnamed sources.

PayPal declined to comment on the report. A Stripe spokesperson said the company doesn’t “comment on rumors or speculation.”

Advertisement

The negotiations are taking place as Lores attempts to save the company from its lagging trajectory.

Lores joined PayPal in March, after spending years at HP. In April, Lores made the first moves in his turnaround plan, including an executive shuffle and splitting the business into three operating models: checkout solutions and PayPal, consumer financial services (and Venmo), and payment services and crypto. A month later, Lores told investors that PayPal would recommit to the fundamentals,” which included “becoming a technology company again.”

PayPal’s turnaround will also include a cost-saving plans, which is expected to reduce its workforce by 20% over the next two to three years.

PayPal was founded in 1998 by a number of men who went on to be Silicon Valley luminaries, including Peter Thiel, Elon Musk, Max Levchin, Luke Nosek, and others. The company has struggled in recent years, after ballooning during the pandemic due to an e-commerce boom.

Advertisement

Source link

Continue Reading

Tech

Manus splits from Meta after China orders reversal of $2bn deal

Published

on

Last December’s acquisition faced near immediate scrutiny from Chinese authorities.

AI start-up Manus is going back to being an independent business after Meta’s $2bn-plus acquisition of the company was ordered in April by Chinese authorities to be unwound over national security concerns.

“We must take this step to comply with regulatory requirements in specific parts of the world,” Manus said in a blogpost yesterday (11 August). As part of these changes, it said that some of its users may lose the data they generated using Manus’s AI.

As we look to the future, we’re already preparing a series of new features that will push the boundaries of what’s possible for general AI agents once again.”

Advertisement

Meta acquired the Singapore-headquartered Manus (developed by China’s Butterfly Effect) late last December as part of its continued push into agentic AI.

The acquisition faced near-immediate scrutiny from Chinese authorities, who launched a probe shortly following the deal’s announcement. Meta said that the deal “complied fully with applicable law”.

“Manus has built one of the leading autonomous general-purpose agents that can independently execute complex tasks like market research, coding and data analysis,” the Facebook parent said at the time of its purchase. Manus’s general-purpose AI agent, previewed last year, offered users capabilities similar to those of the likes of OpenAI’s Deep Research.

In February, Manus launched personal agents in messaging apps, allowing users to conduct research, structure data and make requests entirely through chat. It launched the agents on Telegram despite being owned by Meta at the time, but said that it planned to expand to WhatsApp, Line, Slack and Discord “very soon”.

Advertisement

The acquisition deal was formally struck down in April by China’s National Development and Reform Commission, which said that the deal was not in accordance with state laws. The country is increasingly protective of its AI technology and talent, and has been making concerted efforts to build out its own infrastructure to back the technology.

Reversing the acquisition was difficult for Meta, which had reportedly already assimilated Manus employees, executives and technology with its own at the time of the ruling.

Investors – including Tencent Holdings, ZhenFund and Hongshan – had also received their proceeds from the acquisition by the time the two companies proceeded to break up. Tencent is now reportedly set to become Manus’s largest external shareholder.

Don’t miss out on the knowledge you need to succeed. Sign up for the Daily Brief, Silicon Republic’s digest of need-to-know sci-tech news.

Advertisement

Source link

Continue Reading

Tech

Marvel’s Wolverine arrives complete on disc, just as physical gaming fades

Published

on

In a nutshell: Marvel’s Wolverine is scheduled for release in a month’s time, and X-Men fans are eager to play Insomniac Games’ new title on their PlayStation 5 consoles. According to the project’s director, Wolverine will also be one of the last PS5 games designed as a complete experience that works out of the box.

During a recent interview, Insomniac’s Senior Project Director Jess Reiner-Reed confirmed that Marvel’s Wolverine will bring a pleasant surprise to fans of physical game releases. The upcoming action game will be fully playable from the disc, meaning user will be able to enjoy the experience straight out of the box with no mandatory day-one download.

Marvel’s Wolverine will come in both physical and digital editions, Reiner-Reed said. Insomniac developers are working on a day-one patch designed to further polish the experience, but there appears to be no requirement to download the update before customers can start playing the game from the get-go.

While confirming that the game will offer a complete on-disc experience, Reiner-Reed is encouraging gamers to download the patch anyway. Insomniac’s perfectionistic approach to development means the update could tweak and improve the game considerably, as the developers are still busy polishing it just a month before its official release.

Advertisement

Physical releases are suddenly all the rage among gamers after Sony shared plans to stop making physical games starting in 2028. A few studios have expressed their support for disc-based gaming, and even major corporations such as Amazon are apparently willing to throw disc lovers a bone with specific campaigns.

Asked about Sony’s decision to abandon the disc format for future game releases, Insomniac representatives chose to avoid the question altogether. Insomniac’s head of technology, Mike Fitzgerald, said the studio simply wanted to talk about the game it had been working on for years, leaving other concerns to its owner, Sony Interactive Entertainment.

Wolverine will retell the story of the eponymous Marvel character during his amnesiac phase. While trying to regain his long-lost memories, Logan will help Jean Grey and other characters from the X-Men mythos free mutants abducted by Trask Industries.

Advertisement

The game will be significantly more violent than the PS5 Spider-Man series Insomniac has worked on in the past, which seems like an apt choice considering Wolverine’s traditionally brutal ways of dealing with threats and enemy forces. Despite featuring many recurring characters from the franchise, Marvel’s Wolverine will not include a proper rendition of the X-Men collective just yet.

Source link

Advertisement
Continue Reading

Tech

Lenovo Idea Tab Delivers Everyday Utility Without the Premium Price Tag

Published

on

Lenovo Idea Tab 2026 Tablet
Students and casual users looking for a basic Android tablet are usually forced to choose between bare-bones devices that seem limiting and more expensive models filled with capabilities they may never use. Lenovo’s Idea Tab, priced at $149.99 (was $218), sits squarely in the middle of that range, offering a useful combination of screen quality, battery life, and accessories that make it functional right out of the box.



At almost 10-inches across and just shy of an inch thick, the metal-bodied tablet feels reassuringly sturdy without adding bulk. It weighs more than a pound, so it fits neatly into a backpack or can sit comfortably on a desk all day. Available in Luna Gray or Polar Blue, the simple and robust external design is great for daily use, and the IP52 classification provides some basic resistance to dust and mild water exposure, making it ideal for a school or a kitchen setting.

Sale


Lenovo Idea Tab – College Tablet – 11″ 2.5K IPS Touchscreen Display – 90Hz – MediaTek Dimensity…
  • POWER YOUR STUDY, FUEL YOUR PLAY – Discover smarter learning with the Lenovo Idea Tab. Stay campus-ready with all-day battery life, AI-powered apps…
  • SMOOTH, POWERFUL, IMMERSIVE – The MediaTek Dimensity 6300 processor is more powerful than ever, with the AI-enhanced multitasking you need to stay…
  • CIRCLE IT, SEARCH IT – Use your Lenovo Tab Pen or fingertip to circle items for instant search results or to translate other languages without…

The 11-inch IPS panel is one of the tablet’s most notable features. With a resolution of 2560 by 1600, it produces a sharp 2.5K image that comes to life owing to a 90Hz refresh rate that ensures scrolling and video playback go smoothly. The screen’s peak brightness of 500 nits is more than adequate for any lighting circumstances, and the anti-fingerprint coating eliminates the possibility of smudges disturbing your view. In addition, it has TÜV Rheinland certifications for low blue light and flicker-free operation, which is important for anyone who watches a lot of video. Color coverage is a reasonable 72 percent NTSC, and the 16:10 aspect ratio is ideal for maximizing vertical space for papers and multimedia. If that wasn’t enough, four Dolby Atmos-tuned speakers lie around the edges, producing far superior sound than you’d expect at this price. Even in busy situations, dialog sounds clear as a bell, and the overall volume is adequate for a small room without adding too much distortion.

Advertisement


Power comes from a reasonably powerful MediaTek Dimensity 6300 CPU, which is paired with 4GB of LPDDR4X memory and a handy 128GB of UFS storage – all of which are very normal for the price. In reality, it effortlessly handles online browsing, note-taking apps, video calls, and light multitasking. Try pushing it with hard games or intensive creative work, and it will begin to struggle. It is completely responsive for normal college or home tasks, and if you need more storage capacity, a microSD slot allows you to add cards up to 2TB, making it ideal for anyone who collects a large number of PDFs, lecture recordings, or offline media. Connectivity is uncomplicated, with Wi-Fi 5 and Bluetooth 5.2 on board, as well as a regular USB-C connection and headphone jack.

Lenovo Idea Tab 2026 Tablet
According to Lenovo, the battery can last up to 12 hours of YouTube viewing or 14 hours of online browsing, assuming optimal conditions. In practice, it’ll probably last you the entire day, even if you’re switching between courses and study sessions. Charging supports 20W input, but be aware that the adaptor is not always included, depending on the location or merchant package. Android 15 lies on top of Lenovo’s interface, with promised compatibility for two major OS upgrades and security patches to 2029. Circle to Search, which allows you to highlight text or images for quick lookups and translations, and a slew of preloaded tools like Lenovo AI Note, Squid, Nebo, and MyScript Calculator support handwriting, diagram sketching, and equation solving. There is also Smart Connect, which allows you to smoothly transfer jobs between this tablet and other Lenovo or compatible devices.

Lenovo Idea Tab 2026 Tablet
This bundle includes two valuable extras: a folio case and a Lenovo Tab Pen. The cover not only protects the screen and body, but it also serves as a handy stand, allowing you to put it up at almost any viewing angle you like – and it even includes a small pocket for the pen. The pen itself is very slick, with 4096 distinct levels of pressure sensitivity, tilt recognition, and a palm rejection feature that ensures you don’t lay your hand on the screen while writing.

Source link

Advertisement
Continue Reading

Tech

Ex-Cambridge Professor At Center of Plagiarism Row Found Dead

Published

on

Former Cambridge professor Jason Arday, who resigned last week amid allegations of plagiarism and questions about his academic record, has been found dead at age 41 in London. The BBC reports: Jason Arday was found “unresponsive” at an address in Battersea, south London, on Friday afternoon, emergency services said. Metropolitan Police officers were called by the London Ambulance Service. A 41-year-old man was pronounced dead at the scene and his next of kin have been informed, the force said.
Arday resigned as a Cambridge professor of sociology of education last week after allegations of plagiarism and questions about some of his achievements. He had denied the claims.

In a statement, the Met Police said: “At this time his death is being treated as unexpected, but is not believed to be suspicious.” The 41-year-old academic had denied any plagiarism – but admitted errors in his work – and last week said the recent furore had led to “an unrelenting level of public scrutiny and personal attack.” The row first erupted after another academic — self-defined “race realist” Nathan Cofnas, who was sacked from his Cambridge role in 2024 — said he found numerous instances of plagiarism in Prof Arday’s work and questioned some of his stated achievements.

[…] Announcing his resignation last week, Arday said the “personal cost” of the scrutiny had become “too great.” He said: “While criticism is an inevitable part of academic life, what I have experienced has gone far beyond scholarly disagreement. “The relentless accusations, speculation and public commentary have taken a profound toll on me and on those I love.” He stressed that his resignation should not “be mistaken for an acceptance of the narratives that have surrounded me.”

Read more of this story at Slashdot.

Advertisement

Source link

Continue Reading

Tech

JSW MG Hector Tomahawk Teased in India: 7-Seater EV Launching August 26

Published

on

MG Motors has quietly been doing great in the EV space with its Windsor, which is now one of the best-selling EVs in India. And to further bite into Mahindra and Tata’s share, JSW MG Motor India has teased its upcoming 7-seater electric SUV, which is expected to launch in India as the Hector Tomahawk. The company has confirmed that the SUV will be the first product based on its new ADAPT (Advanced Drive Architecture Platform Technology) platform and will make its India debut on August 26.

According to reports, the upcoming SUV is based on the Wuling Eksion, which is already sold in Indonesia. The Hector Tomahawk will initially launch in India as a fully electric model, with a plug-in hybrid version expected to follow at a later date. JSW MG has also opened pre-reservations for the SUV. Customers can reserve it on the company’s website for ₹21,000.

JSW MG Hector Tomahawk Design and Interior

The latest teaser reveals several design details of the upcoming SUV while keeping most of its exterior hidden. The Hector Tomahawk features rectangular LED headlamps with twin-element LED DRLs, along with prominent fenders, roof rails, pull-type door handles, and wraparound LED taillamps. The SUV also gets two-tone alloy wheels, black cladding along the lower doors, and a relatively flat roofline leading to a roof spoiler. The charging port appears to be positioned on the rear-left side.

Advertisement

Some India-specific design changes are also expected compared with the Wuling Eksion. These include different artwork on the C-pillars and a knurled finish on the front grille. Based on the dimensions of the Indonesia-spec Eksion, the Hector Tomahawk could measure around 4,745mm in length, 1,850mm in width, and 1,755mm in height, with a 2,810mm wheelbase. However, JSW MG has not yet confirmed the final dimensions for the Indian model.

The teaser also confirms a seven-seat layout with a bench-style second row. The cabin shown in the teaser features a beige color theme and a panoramic sunroof. More details are yet to be confirmed, but the India-spec SUV could share several features with the Eksion. These may include a powered tailgate, powered and ventilated front seats, a 12.8-inch infotainment display, an 8.8-inch digital driver’s display, wireless charging, automatic climate control with vents for the second and third rows, a 360-degree camera, an electronic parking brake, six airbags, and ADAS.

Expected Powertrain & Pricing

The ADAPT platform can support different powertrain configurations, including strong-hybrid, range-extender, and plug-in hybrid systems. In India, however, the Hector Tomahawk will be an EV first. While the specific details are still under wraps, the Indonesia-spec Wuling Eksion makes 201hp and 310Nm of torque with a single front motor. Everything is powered by a 69.2kWh LFP battery and has a claimed CLTC range of up to 530km. A plug-in hybrid version is also expected to arrive later.

The JSW MG Hector Tomahawk is expected to be priced between ₹18 lakh and ₹25 lakh (ex-showroom), although the company has not announced the official pricing yet. If true, it’ll go head-to-head with the Mahindra XEV 9S and the Harrier EV.

Advertisement

Source link

Continue Reading

Tech

Why Does The F-16 Fighter Jet Have A Reclined Cockpit Seat?

Published

on





Unlike airliners, fighter aircrafts routinely experience multiple times the force of gravity, especially while maneuvering aggressively. These intense G-forces place enormous strain on the human body, making even simple tasks increasingly difficult. At the same time, success in a dogfight requires maintaining constant visual contact with an opponent, often while the aircraft is banked steeply through tight turning maneuvers. The Viper’s reclined seat was designed to help pilots withstand those extreme forces of air combat, while also improving their ability to keep an adversary in sight. Two advantages that contributed directly to the Viper’s success.

Since entering service on August 17, 1978, the F-16 Fighting Falcon (nicknamed the Viper by those lucky enough to work with them) has earned its reputation as one of the world’s most successful multirole fighter aircraft, due to features like the aforementioned reclining seat. A product of the USAF’s Lightweight Fighter Program, the Viper’s strengths and weaknesses were designed around one primary goal: Dominate the within-visual-range combat domain through exceptional maneuverability, supreme energy management, and an unbeatable sustained turn rate. It’s superior in many ways over F-4E fighter jets, with its design focused relentlessly on creating a small, agile dogfighter that gave pilots every possible advantage in a post-merge, turning dogfight.

This philosophy was ultimately realized across a number of design choices. Relaxed static stability, a blended wing-body design, and long leading-edge extensions gave the Viper its exceptional dogfighting performance. That performance was complemented by the introduction of several unconventional cockpit features that were revolutionary for the time, including a side-mounted control stick, a frameless bubble canopy, and, perhaps most noticeably, a cockpit seat reclined at 30 degrees. While unusual compared to almost every other fighter aircraft, all of these components and design choices were the result of extensive research into both pilot physiology and combat effectiveness.

Advertisement

Surviving the forces of air combat in a fighter jet

High-G maneuvering is one of the greatest physical challenges a fighter pilot faces. Throughout the aggressive turning and banking of a dogfight, a pilot’s body experiences extreme G-loading; forces attempt to pull blood away from the brain and towards the lower body, blood pressure in the head drops, and vision begins to narrow. This escalates to gray-out, before eventually progressing to total G-LOC, or G-induced loss of consciousness. In the fast-paced, high-stakes competition that is an aerial gunfight, losing consciousness for even a few seconds can have catastrophic consequences.

The Viper’s 30-degree reclined seating position helps reduce this risk by changing the direction in which G-forces act on the body. Rather than pulling blood almost directly from the head to the feet, the reclined posture shifts more of the force through the pilot’s chest and back. This shortens the vertical distance between the heart and the brain, making it easier for the cardiovascular system to maintain blood flow to the pilot’s head during those high-G maneuvers.

Advertisement

The benefits of this seating design extend beyond improved G tolerance. Supporting more of the pilot’s weight across the back also reduces strain on the neck and spine during prolonged patrols or ferry flights, particularly when wearing a heavy flight helmet or night optic device. Today, pilots rely heavily on anti-G suits and specialized straining techniques to remain conscious under high G-loads, but only Viper drivers have that deep, reclined sitting position providing another layer of mitigation to the dreaded grasp of G-LOC. That extra layer of protection, perhaps an few more seconds of useful consciousness, may be what separates victory, defeat, or UFIT (Uncontrolled Flight Into Terrain).

Advertisement

Keeping an eye on enemy fighters

A key aspect of both basic and advanced fighter maneuvering is maintaining tally, or keeping the enemy within your field of vision. This allows a pilot to determine how and where they should maneuver to gain an advantage, or how an enemy may be counter-maneuvering. Lose sight of your opponent and you lose situational awareness, or, as the old saying goes, “lose sight, lose fight.”

Fighter maneuvers therefore prioritize positioning the aircraft to pull the reticle up and onto the target, a technique known as lag pursuit. This generally results in the target aircraft being held slightly above the horizontal focal plane of the pilot, and is where an adversary will naturally be positioned within one and two circle flow dogfights. This requirement to constantly look up and around through the higher aspect of the canopy demands enormous amounts of stamina in a fighter pilot’s neck and upper back muscles.

By leaning the pilot backwards by 30 degrees, the Viper’s seating position naturally positions the head and eyes to look higher through the canopy with less neck extension. This reduces muscle stress without reducing visibility across those critical vision sectors. Although this reclined seating position does sacrifice some comforts (particularly during use of the in-flight bladder release system) and reduces forward visibility during routine straight-and-level flight, those compromises were considered worthwhile.

That’s because the Viper was never intended to be optimized for cruise efficiency. It was built to win a knife fight in a phone booth, and almost every aspect of the aircraft represents that dogma. From its size, weight, and wing profile to its blended fuselage, bubble canopy, and reclined seating position, every aspect of the Viper reflects the uncompromising design philosophy behind one of the greatest rate fighters ever built. It’s no surprise the F-16 Fighting Falcon would go on to make history.

Advertisement



Source link

Advertisement
Continue Reading

Trending

Copyright © 2025